12:05 PM EST - Continental Gold Inc. : Provided a construction update for the Buriticá project in northwestern Antioquia, Colombia. Construction of the overall Buriticá project is 56% complete and remains on schedule for completion and first gold pour in H1 2020. Ramp-up to commercial production is anticipated approximately six months thereafter. ajor equipment including the SAG mill and primary crusher are in place and installation of ball mill shells is underway. Structural steel erection is advancing rapidly in many areas, particularly for the crushing, grinding and tailing filtration circuits.In early March, crews reached a significant milestone by surpassing 10 kilometres of underground development advance. As of March 22, approximately 74% of the pre-production development plan has been completed, totaling 10,529 metres of lateral underground development. Continental Gold Inc.