Fortuna Silver Mines Inc.

11:46 AM EST - Fortuna Silver Mines Inc. : Provided an update on construction, pre-commissioning and commissioning activities at its 100% owned Lindero gold Project located in the Province of Salta, Argentina. As of the end of November 2019, the overall project is 85% complete. Primary and secondary crushing circuits: Pre-commissioning activities are being carried out and are in their final stages; placing of first ore to crushing is scheduled for the end of December. HPGR circuit: Final mechanical completion activities and vendor representative unavailability through the holidays have pushed back pre-commissioning activities to mid-January 2020. Agglomeration plant: Mechanical installation is complete and minor piping and electrical installation work is in the final stages; pre-commissioning is expected to commence in mid-January 2020. Fortuna Silver Mines Inc. shares T.FVI are trading up $0.28 at $4.72.