10:32 AM EST - Kolibri Global Energy Inc. : Provided an update on its operations located in the Company’s Tishomingo field in Oklahoma.The Company has completed the location work for the Glenn 16-3H and Brock 9-3H wells, which are the third and fourth wells in the Company’s 2022 drilling program. The location for the fifth well, the Emery 17-2H, should be completed by the end of the month. The drilling rig loads finished arriving on location last week and a third-party crane is expected on site tomorrow to begin rigging up the drilling rig. The rig is expected to spud the Glenn 16-3H by September 1st. All three wells are planned to be drilled back to back and the completion operations for the Glenn 16-3H and Brock 9-3H wells have been tentatively scheduled for the first week of October. Kolibri Global Energy Inc.
shares T.KEI are trading up $0.01 at $2.08.