09:31 AM EST - Ares Strategic Mining Inc : Announces the Company has completed the tailings storage facility design work for its upcoming manufacturing and processing fluorspar operation in Delta, Utah, United States. Knight Piésold and Co. was retained by Ares to provide engineering services for the TSF design and provide support for the permitting process. The new TSF will be located on Ares’ 48-acre property and will be constructed in stages. Stage 1 will include construction of a single storage cell, to be used for the first three years of operation. Stage 2 will include construction of a second storage cell, to be commissioned upon Cell 1 reaching storage capacity. Stage 3 will raise the entire perimeter embankment, which will combine Cells 1 and 2 into a single cell, to be used for the remaining years of capacity. Ares Strategic Mining Inc