Orla Mining Ltd.

10:04 AM EST - Orla Mining Ltd. : Provided a construction update for the Camino Rojo Oxide Project. Camino Rojo construction was 89% complete as of September 30, 2021, on schedule for first pour in December 2021 and commercial production in the first quarter of 2022. Construction remains on schedule with the main activities completed during the quarter including: Ramp up of mining activities in line with plan, Mechanical completion of the crushing and conveying system, reclaim tunnel, overland conveyor, and grasshopper conveyors. Orla Mining Ltd. shares T.OLA are trading down $0.20 at $3.90.